Case Study
CLIENT: WATSON NORIE LTD
PROJECT: POLYMERS DCS
The Brief
To install 65,000 metres of multi-core cabling in approximately 4 weeks on the Wilton Project.
The Solution
Efficient installations and dressing and cleating of cables into existing operational plant rooms was completed to very strict deadlines. This was only possible due to the commitment and flexibility of our well-trained and dedicated workforce.
Client's Comments
"Please will you pass on my thanks and congratulations for a job well done to all your personnel who have worked on this contract."
"Taking cognisance that the installation has been completed in a very congested area on an existing running plant and with the added problem of very little overtime being available it has been an achievement indeed."
Ralph Hopper
Project Manager
Watson Norie Ltd